Coming up:
Construction Begins - April, 2007 City approval of the final relocated road City approval of Church building and site designs Target Construction Completed - 2008
Completed:
Organize Church Committees - May/June 2002 Form Church Building and Design Committee - May/June 2002 Select Tour Sites and Dates - May/June 2002 Parish Tours - June 2002 Gather input from the Tours to begin - June 2002 Schematic Design - January 2002 Select Contractor - April 2003 City Planning Approvals - Spring 2006 Capital Campaign II Kickoff - Building a People of Faith - September 8, 2006 Design Committee Meeting - September 19, 2006 Design Committee Meeting - November 16, 2006 Diocesean Design Development - December, 2006 Construction Documents City Submittal - April, 2007 Grading Permit from City - April, 2007
For more detail, please see the project history.
|