Sept. – Nov. 1998
|
Liturgical formation process
|
|
May/June 1999
|
Town Hall Meetings for master planning
|
|
September 1999
|
Interviewed professional fundraisers
|
|
December 1999
|
Preliminary Review Procedure (PRP) application filed with the City of Fremont
|
|
February 2000
|
City provided comments on PRP application
|
|
Feb. to June 2000
|
City input and meetings with neighbors. Master Plan was updated, we began 2-acre land acquisition process with Dominican Sisters
|
|
Summer 2000
|
Preliminary assessment of first phase of project cost as $10,200,000
|
|
September 2000
|
Capital campaign began with target goal of $4,000,000 in pledges. The 4 million target was simply the calculation of annual offertory times a factor. Due to the size of the parish, the per capita income of the majority of families registered at St. Joseph, and the large amount of “loose change” donors it was also felt that a target of 5 million was achievable. Raising pledges of half the cost would permit construction to begin.
|
|
November 2000
|
Monsignor Simas and Coordinating Committee members appeared before Planning Commission on Mission San Jose Planned District (MSJPD) to voice concerns
|
|
March/April 2001
|
Final concerns worked out with City staff members, City Council adopts MSJPD guidelines
|
|
May 2001
|
Consultants were retained to prepare parcel map including civil engineer, soil engineer and biological assessment
|
|
August 2001
|
Application for parcel map filed with City including maps and reports from all consultants
|
|
October 2001
|
Planning Commission approved parcel map with concerns about creek
|
|
May 16 & 17, 2002
|
Town Hall Meeting
|
|
May 2002
|
City staff finalized review of map for recordation with County
|
|
June 15, 2002
|
Design Church committee tours area churches to gather ideas.
|
|
June 26, 2002
|
Design Committee Meeting - Tour Debrief and Consensus Notes
|
|
July 22, 2002
|
Design Church committee meeting - Schematic Design: Presentation (Zip) & Minutes (PDF)
|
|
August 26, 2002
|
Design Church committee meeting - Schematic Design: Minutes (PDF)
|
|
September 16, 2002
|
Design Church committee meeting - Schematic Design: Minutes (PDF)
|
|
October 28, 2002
|
Design Church committee meeting - Schematic Design: Minutes (PDF)
|
|
November 6, 2002
|
Town Hall Meeting
|
|
January 20, 2003
|
Design Church committee meeting - Design Development
|
|
April 7, 2003
|
Design Church committee meeting - Design Development: Minutes (PDF)
|
|
January 2006
|
“Story Poles” installed at building site.
|
|
February 2, 2006
|
City of Fremont Historical Architectural Review Board (HARB) meeting - Unanimous 7 to 0 vote
|
|
February 23, 2006
|
City of Fremont planning commission - Unanimous 5 to 0 vote
|
|
March 28, 2006
|
City council meeting - The City Council unanimously voted 5-0 in favor of our new church!!
|
|
March 30, 2006
|
Building and Design Committee Meeting: Shrines & Images and Art & Environment - Minutes
|
|
April 1, 2006
|
Advisory meeting
|
|
May 9 & 31 and June 14, 2006
|
Design Church committee meeting - Meeting Minutes: [1] [2] [3] [4] (PDF)
|
|
June 23, 2006
|
New Church Gala Groundbreaking Festivity!
|
|
August 16, 2006
|
Building and Design Committee Meeting: Introduction of Brother Joe’s work and discussion about interior materials and appearance of ducts. Some of this presentation was used.
|
|
September 8, 2006
|
Capital Campaign II Kickoff - Building a People of Faith
|
|
September 19, 2006
|
Building and Design Committee Meeting: Discussion about the font design, glass, stations of the cross, and other fixtures.
|
|
November 2, 2006
|
City of Fremont Historical Architectural Review Board (HARB) voted unanimously to approve the St. Joseph Rectory Relocation. Details about the relocation are here.
|
|
November 16, 2006
|
Building and Design Committee Meeting: In this meeting we had two Presentations about refinements to the interior space architecture as well as the Liturgical furnishings.
|
|
February 1, 2007
|
Building and Design Committee Meeting: In this meeting we had two Presentations about further refinements to the exterior and interior architecture as well as the Tabernacle and St. Joseph statue.
|
|
March 14, 2007
|
Building and Design Committee Meeting: In this meeting we had two Presentations about further refinements to the interior architecture as well as the Sanctuary, Lighting, and Liturgical furnishings.
|
|
April 18, 2007
|
Building and Design Committee Meeting: In this meeting we had two Presentations about interior & exterior architecture, Sanctuary, Ambo, Stations of the Cross, and Presider’s Chair.
|
|
April 19, 2007
|
Today we received our GRADING and RECTORY Relocation permit OK from the City of Fremont! - Hallelujah!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! -- Many thanks go out for the persistence and hard work by TBI construction and the Steinberg team to finally get to this point! -- This is the first thing that must happen in order to make room for the construction of the new church on the old rectory location!
|
|
April 23, 2007
|
Equipment arrives - Construction begins !!! - Expect to see lots of activity!!!!!!!!
|
|
June 18, 2007
|
Building and Design Committee Meeting: In this meeting we had three Presentations about the interior architecture, exterior landscape and liturgical furnishings, in particular the Stations of the Cross.
|
|
July 25, 2007
|
The stain glass restoration is making significant progress. Click here for more detailed photos.
|
|
October 26, 2007
|
Rectory move is complete and ready for occupancy. Finishing touches have been made after the building move. Click here for more detailed photos.
|
|
|
WHAT’S NEXT? Click here to see the project schedule.
|